Foundation phase live. Stand and conveyancing cleared.

Deviation control

Add variance

Deviation control

Plan vs actual variances

Foundation cost tracking ahead of plan

Planned: $2,800.00 • Actual: $3,435.00

MediumEdit

Spend is 22.7% above the current checkpoint for this stage.

Concrete pour approval not yet cleared

Planned: $1.00 • Actual: $0.00

HighEdit

Builder should not move to slab prep until sign-off is done.

Stand fees closed exactly on budget

Planned: $6,400.00 • Actual: $6,400.00

LowEdit

Closed with no cost variance.