New build phase
Add stage
Build phases
Stage tracker
Stand and statutory fees
Planned window: Jan 2026 • Actual: Jan 2026
CompleteEdit
Planned budget
$6,400.00
Actual spend
$0.00
Budget delta
-$6,400.00
Stand and conveyancing cleared.
Foundation
Planned window: Jul-Aug 2026 • Actual: Started Jul 2026
In ProgressEdit
Planned budget
$9,800.00
Actual spend
$3,395.96
Budget delta
-$6,404.04
Excavation complete. Concrete and reinforcement underway.
Slab
Planned window: Aug 2026 • Actual: Pending foundation sign-off
Not StartedEdit
Planned budget
$7,200.00
Actual spend
$0.00
Budget delta
-$7,200.00
Blocked until foundation inspection passes.
Walling
Planned window: Sep 2026 • Actual: Pending
Not StartedEdit
Planned budget
$8,600.00
Actual spend
$0.00
Budget delta
-$8,600.00
Awaiting slab completion.