Building Project Control

Moyo Residence Command Deck

Foundation phase live. Stand and conveyancing cleared.

New build phase

Add stage

Build phases

Stage tracker

Stand and statutory fees

Planned window: Jan 2026 • Actual: Jan 2026

CompleteEdit

Planned budget

$6,400.00

Actual spend

$0.00

Budget delta

-$6,400.00

Stand and conveyancing cleared.

Foundation

Planned window: Jul-Aug 2026 • Actual: Started Jul 2026

In ProgressEdit

Planned budget

$9,800.00

Actual spend

$3,395.96

Budget delta

-$6,404.04

Excavation complete. Concrete and reinforcement underway.

Slab

Planned window: Aug 2026 • Actual: Pending foundation sign-off

Not StartedEdit

Planned budget

$7,200.00

Actual spend

$0.00

Budget delta

-$7,200.00

Blocked until foundation inspection passes.

Walling

Planned window: Sep 2026 • Actual: Pending

Not StartedEdit

Planned budget

$8,600.00

Actual spend

$0.00

Budget delta

-$8,600.00

Awaiting slab completion.